NEW QUESTION 28
You are performing an SAP S/4HANA conversion. Which phases are executed during SUM technical downtime? Note: There are 2 correct answers to this question
- A. TABIMJJPG
- B. PARMVNT_UPG
- C. PARDIST_SHD
- D. TABIM_SHADOW_*
Answer: A
NEW QUESTION 29
You are performing an upgrade with SUM. You are in the BIND_PATCH phase of the roadmap step "Configuration". For some software components you find entries in the "Calculated level" column.
What does the "Calculated level" indicate for those software components?
Please choose the correct answer.
Response:
- A. The SAP Support Packages that will be bound to the upgrade
- B. The SAP Support Packages found in the download directory
- C. The SAP Support Packages contained in the upgrade media
- D. The SAP Support packages of the Support Package Stack, calculated by the Maintenance Planner
Answer: B
NEW QUESTION 30
You are performing an upgrade of an SAP ECC development system with SUM. What is the earliest point when the upgrade is considered complete and you can allow all dialog users to log on to the system?
Please choose the correct answer.
Response:
- A. During the SUM roadmap step "Postprocessing", after the post procedure steps are complete
- B. During the SUM roadmap step "Postprocessing", in parallel with post procedure steps
- C. After the SUM roadmap step "Execution" is finished and before "Postprocessing"
- D. After the SUM roadmap step "Postprocessing" and post procedure steps are finished
Answer: A
NEW QUESTION 31
During an SAP S/4HANA conversion with DMO, which of the following actions take place during the business downtime of the SUM procedure?
There are 3 correct answers to this question.
Response:
- A. Execution of SPAU modification adjustment
- B. Creation of the table structures in the new SAP HANA database
- C. Execution of XPRAs and AIMs
- D. Execution of SPDD modification adjustment
- E. Execution of eCATTs for business validation tests
Answer: A,C,E
NEW QUESTION 32
You are performing an SAP S/4HANA conversion with the migration repetition option. After which phase does SUM stop to enable a test cycle?
- A. EU_IMPORT_ALL
- B. EU_CLONE_MIG_DT_RUN
- C. EU_CLONE_MIG_DT_CREATE
- D. EU_CLONE_MIG_SOT_RUN
Answer: B
NEW QUESTION 33
What do you need to know about the SAP ERP Upgrade and Update Guide?
There are 2 correct answers to this question.
Response:
- A. It is target release specific
- B. It is a database-specific document
- C. It contains a troubleshooting section
- D. It contains a section "free space requirements"
Answer: A,D
NEW QUESTION 34
You downloaded content from the SAP note 1000009 ("ASU Toolbox 2008"). Which transaction needs to be executed to use that content in the ASU Toolbox?
Please choose the correct answer.
Response:
- A. /ASU/START (Start ASU Toolbox)
- B. /ASU/SHOW_NOTE (Show SAP Note via Web-Browser)
- C. /ASU/SSM (ASU Simple Schedule Manager)
- D. /ASU/UPGRADE (Start ASU Toolbox in Upgrade Mode)
Answer: A
NEW QUESTION 35
What do you do to prepare the database migration option of a SUM procedure?
There are 3 correct answers
Response:
- A. Extract the SAP HANA database installation archive
- B. Move the SAPM update archive into the download folder
- C. Move the stack.xml update file into the download folder
- D. Move the R3trans update archive into the download folder
- E. Extract the SAP HANA client installation archive
Answer: B,C,E
NEW QUESTION 36
You are performing an inplace SAP S/4HANA conversion including DMO. What is the latest point in time when you can reset the procedure without losing data?
- A. The start of the business downtime
- B. The end of the business downtime
- C. The end of the database migration
- D. The start of the Execution roadmap step
Answer: B
NEW QUESTION 37
During the upgrade of your development system, you run into the adjustment of non-dictionary objects handled by transaction SPAU There you find programs that are shown in status "automatic adjustment (green traffic tight). What will happen with these programs when you continue with your upgrade without performing any other actions inside your SAP system?
- A. SUM continues with the next phase and your modifications are lost
- B. SUM continues with the next phase and your modifications are kept as In the start release
- C. SUM refuses to continue unless you have marked a transport request as modification adjustment transport
- D. Before continuing with the next phase SUM asks for a modification adjustment transport
Answer: B
NEW QUESTION 38
You want to execute a Unicode Conversion only. Which approach do you need to follow?
Please choose the correct answer.
Response:
- A. SUM without DMO
- B. SWPM using the Load procedure
- C. SUM with DMO
- D. SWPM using the Backup / Restore procedure
Answer: B
NEW QUESTION 39
You are performing an SAP S/4HANA conversion. When does the silent data migration (SDM) take place?
- A. Before the start of the SUM technical downtime
- B. During the Execution roadmap step
- C. After SUM has ended
- D. During the SUM technical downtime
Answer: D
NEW QUESTION 40
ICNV initialization does 3
- A. Creation of flag
- B. AA
- C. Creation of views
- D. Build index on flag column
Answer: A,C,D
NEW QUESTION 41
What are the benefits of using the Benchmarking option of the DMO for SUM?
There are 2 correct answers to this question.
Response:
- A. You can obtain migration duration files that can be used to optimize the next runs from a previous benchmark run.
- B. You can record the modification adjustment during migration and use the transports in the next runs.
- C. You can verify that the content of the download directory matches the stack.XML file.
- D. You can find the optimal number of parallel R31oad processes by monitoring host performance.
Answer: B,D
NEW QUESTION 42
Which preparational steps must be performed for an SAP S/4HANA conversion?
There are 2 correct answers to this question.
Response:
- A. Delete client 066 (Early Watch Client)
- B. Uninstall Fiori apps not released for SAP_UI 7.50
- C. Uninstall industry extensions not supported by SAP S/4HANA
- D. Install add-on SAP Gateway 7.50
Answer: A,B
NEW QUESTION 43
Regarding an SAP Upgrade, What does the major SAP Note for the version of SUM you are using usually contain?
- A. The link to different patch levels to SUM
- B. An overview about possible upgrade paths
- C. The corrections to the SUM Guide
- D. AA
Answer: A,B,C
NEW QUESTION 44
During a DMO procedure with SUM, after which phase is the repository first available on the target database?
Please choose the correct answer.
Response:
- A. Downtime migration (EU_CLONE_MIG_DT_RUN)
- B. Uptime migration (EU_CLONE_MIG_UT_RUN)
- C. ParaUel distribution (PARDIST_SHD)
- D. Shadow repository creation (EU_IMPORT*)
Answer: B
NEW QUESTION 45
......